5/11/2021

Construction of second runway at Fukuoka Airport starts and will be completed in March 2022!

 <Successful bid for Fukuoka Airport runway expansion by Obayashi Corporation for 2.53 billion yen>

Obayashi Corporation won the bid for the ground improvement work for the runway expansion of Fukuoka Airport in 2021 at 2,530,490,000 yen (excluding tax).  The work including removal of structures and ground improvement will be carried out in conjunction with the expansion of the runway at Fukuoka Airport. The construction period is planned to end on March 25, 2022.

The second construction work was awarded to Goyo/Fudo Tetra JV for 1,720,860,000 yen (excluding tax). In this project, airport paving and ground improvement work will be carried out. The construction period is planned to end on March 25, 2010.